Overall: Contractors installed gutters and insulation, and we completed installation of siding, fasica and soffit for both buildings. It was a good week…

Monday: A rolloff construction material dumpster arrived this morning. I’ve been able to manage construction trash by burning (framing lumber scrap) or hauling home to go in the weekly household trask pickup. Drywallers will need a place to dump their waste. Kyle installed blocking for grab bars for each bathroom – thinking ahead when we are really old.

Tuesday: The seamless gutter installer arrived today and completed his task in short order. Kyle and I worked siding on the north wall of the shop.

Wednesday: We completed the shop north wall, which brought this large task to an end. 100% complete with exterior siding, fascia and soffit. Very fortunate to have had mild weather for the most part since we began the task in early January.

Thursday: 70 degrees this afternoon ! Our insulation contractor was on site early this morning. They worked until after 6PM to complete the task in one day. Kyle and I worked odds and ends on a punch list of things to be done before drywall is hung.

Friday: An all day, cold, wet, rainy day. Ran errands around town visiting several vendors, making phone calls, researching the next phase of materials needed.

Saturday: Worked on the computer, scanning receipts, updating the speadsheet. More online material research.

Sunday: A beautiful sunny warm day. Spent several hours at the site, cleaning up and packing up everything. Both buildings need to be empty when the drywall task begins.